Phase 1: Post Anchors & Posts

Install 9 Simpson ABA66Z post anchors with 1/2" wedge anchors on cured concrete footings. Rough-cut nine 6x6 PT posts, install and plumb them on the anchors, then use the laser to mark final height and cut and notch each post IN PLACE.

Post Grid Layout (top-down)

Pool (24 ft diameter) — 1" gap to decking Beams 3 beams, ~14'-8" each 14'-0" total width 4'-11 7/8" 5'-0 1/8" 14'-8" depth 5'-4" 5'-4" 6x6 PT post in 12" sonotube (typ.) 2'-0" cant. Note: middle post row is 1/8" left of true center per plan
Top-down view. Pool at top (curved). Deck framing outline dashed. Beams run through columns of 3 posts, perpendicular to pool.
Wait time: Quikrete 5000 needs at least 3-5 days cure before installing post anchors. Wait 7 days before applying framing loads (beams and joists).

Hardware for This Phase

ItemQuantitySource
Simpson ABA66Z 6x6 Post Base Z-MAX9On hand (Bushka order)
1/2" x 5-1/2" Torquemaster Blue Wedge Anchor Hot Galv9On hand (Bushka order)
Simpson SD10 x 2-1/2" Strong-Drive Connector Screws~75 (8 per anchor × 9)NEED TO BUY
6x6 PT posts (12' lengths)9On hand (cut to length on-site)
Screw type matters: ABA66Z accepts either 16d common nails (0.162" × 3-1/2") or Simpson SD10 × 2-1/2" Strong-Drive Connector screws. Do NOT use SDS Heavy-Duty screws (those are for post caps and other heavier connectors) or SD9 screws (too small for the ABA's larger fastener holes).

Tools

Part A: Install ABA66Z Post Bases

Step 1: Mark Post Centers on Concrete

1Mark the post center on each footing top.

Use plumb bob dropped from the string crossing above (if strings still up), OR triangulate from adjacent footings using measured distances.

Step 2: Drill Center Anchor Hole

2Drill a single 1/2" hole at each post center mark.

Silica dust: Wear a P100 respirator when drilling concrete.

Step 3: Position ABA66Z Base and Install Anchor

3Place the ABA66Z base plate over the drilled hole, then drive the anchor through both.

Why this order: Setting the base plate first, then driving the anchor through it, means the anchor stays put once it's set — no need to remove the nut, slide the base on, and re-thread the nut. One clean install.

Step 4: Torque the Anchor

4Tighten the nut to the specified torque.

Concrete strength note: Quikrete 5000 reaches 5,000 psi at 28 days — well above what wedge anchors are designed for (specs are typically based on 2,500-4,000 psi concrete). At 7 days cure, Quikrete 5000 is already around 3,500 psi. Higher-strength concrete gives you MORE holding power, not less, and doesn't change the install torque.
Use a torque wrench for the final set — not an impact driver. Impact drivers can over-torque and either strip the anchor threads or crack the concrete around the anchor.

Part B: Rough-Cut and Install Posts

Method: Instead of measuring each post length and cutting on the ground, posts are installed OVER-LENGTH, then marked with the laser and cut to final height in place. This eliminates measure-and-transfer errors — the laser line IS the reference, marked directly on the standing post.

Step 5: Set Laser at Deck-Top Elevation

5Set the 360° laser at the top of the pool coping elevation.

Step 6: Rough-Cut Each Post — Measured, Not One Fixed Length

The yard slopes heavily, so post heights vary a lot — back-row posts will be noticeably taller than pool-side posts. Do NOT rough-cut all 9 to one length. Each post gets its own quick measurement.

6Measure each footing and rough-cut its post to that measurement plus margin.

Step 7: Mark the Notch Face on Each Post

Do this BEFORE standing each post. Once 8 screws are driven through the ABA66Z, the post cannot be rotated. Mark the face that will get notched (the beam-side face) on the TOP of each post with a big marker arrow, and orient all 9 posts consistently as you set them. Beams run PERPENDICULAR to the pool — see the notch diagram below in Part D.

Step 8: Set, Plumb, Screw, and Brace Each Post

8Install each rough-cut post into its ABA66Z saddle — completely.

Fill every hole in the ABA66Z. Skipping holes reduces the anchor's rated load capacity per Simpson's spec table (920 lb uplift, 11,415 lb download when fully fastened). The post must be rigid — plumbed, fully screwed, and braced — before any in-place cutting in Part C.

Part C: Mark and Cut Posts to Final Height — In Place

The laser was set at pool-coping elevation back in Step 5. If any time has passed or the tripod may have been bumped, verify the line still sits level with the top of the coping before marking.

Step 9: Mark the Cut Line on Each Post

Cut line = laser line − 8-1/4"

The 8-1/4" accounts for:

The beam sits IN the notch (cut into the top of the post), so beam depth isn't subtracted.

9Mark each post where it needs to be cut.

Step 10: Cut Each Post at the Line — In Place

10Cut each standing post at its marked line using the four-sided technique.

After cutting all 9, sweep the laser across the post tops as a check: every top should now sit exactly 8-1/4" below the laser line. Any post more than 1/8" off — re-cut or plan a shim in the notch.

Part D: Notch Post Tops — In Place

Per A3.1 detail 01:

Notch DimensionSize
Depth from top of post (measured downward)7-1/4" (matches 2x8 beam depth)
Width into post face (how far the notch cuts in)3" (matches 2-ply 2x8 beam width)
Which face gets notchedLEFT or RIGHT face (choose one, be consistent all 9 posts)
Post material remaining behind notch2-1/2" (5-1/2" post width minus 3" notch)
Notch orientation: Beams run PERPENDICULAR to the pool through each column of 3 posts. The notch is cut into ONE face (left or right) at the top of the post, forming an L-shaped corner cutout. Do NOT notch through the center of the post.
Side view (post from the side) Post (cut to height in place) 7-1/4" deep (beam depth) 3" 2-1/2" notch remain Beam sits in here (2) 1/2"×6" through-bolts ABA66Z base Top-down view (looking down) Notch (cut out) Post material 3" notch 2-1/2" 5-1/2" (6x6) Beam runs this way (perpendicular to pool)
Left: side view showing the 7-1/4" deep × 3" wide L-shaped notch. Right: top-down view showing which face is notched. All 9 posts get the same notch on the same face.

Step 11: Cut the Notch

11Cut the notch on each standing post.

The saw only cuts 2-5/8" deep; finish the last 3/8" of notch depth with chisel or handsaw to get the full 3" depth.

In-place notching note: The horizontal kerf cuts are comfortable at standing height, but there's no way to register the saw shoe for a vertical rip from the post top — that's why this method uses kerf-and-chisel only. Expect ~15-20 minutes per post. If the first post fights you, the fallback is clean: mark the notch, back out the 8 SD10 screws, notch the post on sawhorses, and reinstall — the ABA66Z saddle re-seats the post identically, so no accuracy is lost. (New screws in the same holes are fine per Simpson if the holes aren't stripped.)
All 9 notches must face the same direction (all left OR all right) so beams align consistently through their columns. This was locked in back in Step 6 when you marked the notch faces — verify the arrow before cutting each notch.

Completion Checklist

Common Problems & Fixes

Wedge anchor spins when tightening

Hole is oversized or concrete crumbled around it. Move to a new location if possible, or use epoxy to secure.

Post is 1/4" too tall

Trim with circular saw.

Post is 1/4" too short

Shim under the beam later with hardwood or 1/4" plywood shim placed in the notch.

ABA66Z position drifts off center before tightening

Loosen nut, slide base horizontally to correct position (up to 3/4" adjustment available), retighten.

Post won't plumb

Check that ABA66Z is centered on the anchor slot. Loosen anchor nut, adjust base position slightly, retighten. Then re-plumb post. If post is warped, rotate 90° and try a different face — this only works BEFORE the SD10 screws go in, another reason to plumb carefully before screwing.

Four-sided cut doesn't meet — ledge at the center

The wrapped line didn't close on itself, or the saw shoe drifted. Small ledge (1/16"): knock flat with a chisel or rasp — the beam won't care. Larger: re-wrap the line with the Speed Square 1/4" lower and re-cut all four faces.

In-place notching is fighting you

Mark the notch, back out the 8 SD10 screws, notch the post on sawhorses, reinstall in the saddle, re-plumb, drive the screws back. The saddle re-seats the post identically — no accuracy lost.

SD10 screw won't drive fully

PT lumber can be very dry. Predrill with a 3/16" bit through the ABA66Z flange hole into the post first, then drive the SD10 screw.